Copper Ridge Deep & Shallow utilities Phase II, Whitehorse, Yukon, 2004

Again, our part of the project covered installation of deep and shallow utilities. We were responsible for the earthworks in excavation and filling, preparation of sub-grade, installation of manholes, catch basins, sanitary sewer and water system, service connection of sewer and water system, and the electrical works. The project cost was $2.5 million CAD.

This was the largest deep and shallow utilities jobs to be covered in a single contract tendered and constructed in Whitehorse. Overall, service utilities for 200 lots was completed within 5 months.